[GE users] High priority queue

mrostaee mrostaee at yahoo.com
Mon Jul 19 08:36:36 BST 2010


Hi,
I have some multiple core nodes(let's 4 cores).
some parallel jobs go to a queue with low priority.
I need a high priority job.

when a parallel job(job1) is running e.g. in a low priority queue(B.q) on multiple hosts that uses 16 cores  and while a job(job2) will be send to high priority queue(A.q) and needs 8 cores.

if B.q defined as subordinate of A.q, all of slots of job1 will be suspended?

is so, after finishing of job2, job1 continue running or reschedule?
if not, how can i define queues for this senario? (when job is on high priority queue, required resources of low priority queue be released).

thanks any help.

------------------------------------------------------
http://gridengine.sunsource.net/ds/viewMessage.do?dsForumId=38&dsMessageId=268940

To unsubscribe from this discussion, e-mail: [users-unsubscribe at gridengine.sunsource.net].



More information about the gridengine-users mailing list