[GE users] Per job limit of PE slots

Reuti reuti at staff.uni-marburg.de
Fri Jun 22 13:19:44 BST 2007


Am 21.06.2007 um 17:27 schrieb Hristo Iliev:

>> This is not possible for now. But there is already an RFE to cover
>> some of this aspects:
>>
>> http://gridengine.sunsource.net/issues/show_bug.cgi?id=2147
>>
>> and
>>
>> http://gridengine.sunsource.net/issues/show_bug.cgi?id=2148
>>
>
> I see. Thank you for pointing it out. Is there some kind of a  
> workaround
> for 6.1? I am seeing numerous WEB pages from other research facilities
> that are also using Sun Grid Engine and have somehow limited the  
> number
> of slots per task. Or should I consider using suboridate queues with
> some share policy and see if our parallel tasks can survive a
> SIGSTOP/CONT preemption.
>
> Sorry for bothering you but I'm really new to the administration of  
> SGE.
> Life was far more simple when I was only a user :)

Well, what I did a time ago, was to check the number of granted slots  
in the script for start_proc_args and return with an error (i.e. exit  
100) if it's more than 8.

It's not the best solution, as first the user has to wait until the  
job starts to run, and then it will be pushed into error state. At  
least, it will educate the users to honor the agreed limits ;-)

-- Reuti

---------------------------------------------------------------------
To unsubscribe, e-mail: users-unsubscribe at gridengine.sunsource.net