[GE users] Can I stop backfilling?

Daniel Templeton Dan.Templeton at Sun.COM
Tue May 20 16:15:46 BST 2008


    [ The following text is in the "ISO-8859-1" character set. ]
    [ Your display is set for the "ISO-8859-10" character set.  ]
    [ Some special characters may be displayed incorrectly. ]

If your jobs are starving, what you're seeing is not backfilling. :)  
What version of SGE are you using?  There was (is?) a bug where the 
first RR job was ignored.  Submitting a second identical RR job, in that 
case, would then cause the scheduler to take notice and actually do the 
RR properly.

By definition, backfilling cannot cause starvation, unless a backfilled 
job runs forever.  BTW, when you say your jobs run 15-20 minutes, are 
they setting sort or hard run time limits?  If not, what is your 
default_duration?

Daniel

Kevin Doman wrote:
> We have a very busy cluster that always have thousands of short jobs
> (15-20 minutes) in queue. Occasionally, a user come in and submit a 20
> processor parallel job with h_rt=100 hours. While reservation is
> enabled (-R y) and priority set to 1024, we continue to experience job
> backfills which resulted in the same 'parallel job starvation' issue.
>
> Is it possible for me to stop backfilling altogether and let the
> parallel jobs go first?
>
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: users-unsubscribe at gridengine.sunsource.net
> For additional commands, e-mail: users-help at gridengine.sunsource.net
>
>   

---------------------------------------------------------------------
To unsubscribe, e-mail: users-unsubscribe at gridengine.sunsource.net