[GE users] Quota's Question

templedf dan.templeton at sun.com
Wed Mar 11 17:22:40 GMT 2009


You'd have to do it with queue configuration and RQS.  You could change 
the queue_sort_method to seqno and set up a queue with a high sequence 
number that is subordinated to all the other queues.  The RQS would 
limit usage of the main queues, but not the subordinated queue.  When a 
job comes in, it tries to go to one of the main queues.  If it can't, 
then it ends up in the subordinated queue.  If another job comes in and 
lands in a main queue on the same machine as a job in the subordinated 
queue, the job in the subordinated queue will be suspended.

Daniel

aragh0rn wrote:
> Hi, There is any way to have some kind of "dynamic" quota in the sense
> that, if someone has use all his quota's resource but there is still
> available free resource, he can use it but until someone need it?
>
> Thanks
>
> ------------------------------------------------------
> http://gridengine.sunsource.net/ds/viewMessage.do?dsForumId=38&dsMessageId=126626
>
> To unsubscribe from this discussion, e-mail: [users-unsubscribe at gridengine.sunsource.net].
>

------------------------------------------------------
http://gridengine.sunsource.net/ds/viewMessage.do?dsForumId=38&dsMessageId=127743

To unsubscribe from this discussion, e-mail: [users-unsubscribe at gridengine.sunsource.net].



More information about the gridengine-users mailing list