[GE users] backfilling in SGE 6.2

reuti reuti at staff.uni-marburg.de
Sun Sep 13 16:18:29 BST 2009


Am 13.09.2009 um 14:18 schrieb tgebert:

> the max_reservation value was set to 20. Regarding the h_rt time, I  
> have tried several values, but unfortunately the smaller jobs also  
> do not run that long as the parallel jobs, that need a lot of  
> procs, so the big jobs were "starving" again.
> I also tried to set a very small h_rt time for the big jobs and a  
> very big h_rt time for the small jobs. But unfortunately the  
> wallclocktime violation cancelled the jobs then. Can you configure  
> the wallclock time violation that the jobs don't get cancelled?  
> This would be another approach to solve this problem.

No, for now it's just an RFE to give some non-enforced estimated  
runtime which isn't available yet. Only option is to use the  
default_duration. It was 10 minutes for the first implementation of  
this feature and is now set to INFINITY by default (also in the  
scheduler configuration).

-- Reuti

------------------------------------------------------
http://gridengine.sunsource.net/ds/viewMessage.do?dsForumId=38&dsMessageId=217107

To unsubscribe from this discussion, e-mail: [users-unsubscribe at gridengine.sunsource.net].



More information about the gridengine-users mailing list