[GE users] Maximum scheduled jobs?

rayson rayrayson at gmail.com
Thu Apr 8 22:04:12 BST 2010


Then use Resource Quotas:

http://wikis.sun.com/display/GridEngine/Managing+Resource+Quotas

Rayson



On 4/8/10, gutnik <gutnik at gmail.com> wrote:
> On Thu, Apr 8, 2010 at 1:40 PM, rayson <rayrayson at gmail.com> wrote:
> > See maxujobs.
> >
>
> I was sure I just saw documentation that said with maxujobs the extra
> jobs will be
> rejected from the queue, but now I can't find it.
>
> maxujobs is for the whole cluster. Is it possible to limit per queue?
>   Vadim
>
> ------------------------------------------------------
> http://gridengine.sunsource.net/ds/viewMessage.do?dsForumId=38&dsMessageId=252747
>
> To unsubscribe from this discussion, e-mail: [users-unsubscribe at gridengine.sunsource.net].
>

------------------------------------------------------
http://gridengine.sunsource.net/ds/viewMessage.do?dsForumId=38&dsMessageId=252748

To unsubscribe from this discussion, e-mail: [users-unsubscribe at gridengine.sunsource.net].



More information about the gridengine-users mailing list