[GE users] Parallel job distribution to span subclusters

laotsao laotsao at gmail.com
Wed Aug 18 14:18:11 BST 2010


may be two way
1)use SDM 
http://wikis.sun.com/display/gridengine62u6/Using+SDM+With+the+Grid+Engine+Adapter
2)setup GE  with new cell that combine two cluster and setup three queue
queuea only clustera host
queneb only clusterb host
queue-all clustera and clusterb host


On 8/18/2010 7:22 AM, henry_leyh wrote:
> Hello,
> We have two subclusters, A and B, in our cluster.  The machines in subcluster
> A are almost identical to those in B, the only difference being slightly
> faster CPUs.  I can send parallel jobs to either A or B (not caring which)
> using wildcards in the PE selection.
>
> What I would like now is a job which doesn't fit in A or B to span over free
> slots in A _and_ B.  That is, only if there are not enough free slots in
> neither A nor B it is allowed to combine slots from both A and B.
>
> Any ideas?  As I understand, sequential numbering of PEs is not available yet?
>
> Best regards,
> Henry
>

------------------------------------------------------
http://gridengine.sunsource.net/ds/viewMessage.do?dsForumId=38&dsMessageId=275191

To unsubscribe from this discussion, e-mail: [users-unsubscribe at gridengine.sunsource.net].

    [ Part 2, "laotsao.vcf"  Text/X-VCARD (Name: "laotsao.vcf") ~228 ]
    [ bytes. ]
    [ Unable to print this part. ]



More information about the gridengine-users mailing list