[GE users] Good starting point for PE

templedf daniel.templeton at oracle.com
Mon Nov 1 16:03:43 GMT 2010


PEs are used for jobs where all of the job tasks have to running at the 
same time.  In general rendering tasks are not parallel.  They are often 
good candidates for array jobs, however.

Daniel

On 11/ 1/10 04:29 AM, llikethat wrote:
> Hi,
> Can you please suggest a good starting point for learning how to create Parallel Environments?
> We are using SGE for 3D animation rendering. The job types are mostly serial, they cannot be executed as parallels.
> What is the actual use of PE in SGE, can this feature can be used for the job types we are executing?
> Is the PE different from what i'm trying to use from SGE or is it the same?
> Thanks,Bharani
>
> ------------------------------------------------------
> http://gridengine.sunsource.net/ds/viewMessage.do?dsForumId=38&dsMessageId=291771
>
> To unsubscribe from this discussion, e-mail: [users-unsubscribe at gridengine.sunsource.net].

------------------------------------------------------
http://gridengine.sunsource.net/ds/viewMessage.do?dsForumId=38&dsMessageId=291829

To unsubscribe from this discussion, e-mail: [users-unsubscribe at gridengine.sunsource.net].



More information about the gridengine-users mailing list